• Client & End User

    Client: National Water Company
    End User: National Water Company

  • Scope of Work

    Manage and supervise the contractor's installation works for the NC3 Pipeline

  • Project Period

    Start: 19 February 2015
    End: 10 December 2017
    Status: Completed

  • Project Value

    SAR 43,000,000

Project Brief

As part of the ongoing development of infrastructure for the city of Jeddah, the National Water Company is constructing a gravity mains pipeline 5.15km long to improve the city's sewer infrastructure. The pipeline is 1100mm in diameter constructed from GRP with an external concrete cover. The route includes 150m of pipe-jacking. SGP's scope of services includes project supervision, control and consultancy on NWC's behalf.